Standard Operating Procedure | Processing | Goods Received Vouchers | External Charges

Standard Operating Procedure | Processing | Goods Received Vouchers | External Charges

Info
Question:
Is it possible to separate additional third-party creditors' services onto a Goods Received Voucher (GRV)?
For example,  import charges from a foreign country or freight charges. 
Idea
Answer:
Yes, it is possible by utilising the External Charges in module. 
Info
For more details about external charges, review the article below:
Steps:w
We first need to enable and configure external charges for the company.
Info
Please note that this is a per-company setting. 
Navigate to Utilities --> Setup --> Company Details --> Default Settings 1. 

Select the option, Enable External Charges

Click on Accept to proceed.



You can configure predefined External Charges by navigating to Utilities --> Setup --> Module Parameters 

Click on the Creditors tab and select the GRV External Charges option, and click on the Setup button. 


Click on the Add button to add a new predefined External charge. 

Click on the Accept button to proceed.



You will now have the option to add the External Charges to the GRV. 

To add the external charge, you will note that there is an External Charges button on the bottom right of the screen. 
When you click on it, you will be able to add a custom External charge or use the predefined configuration. 

Navigate to Processing --> Goods Received Voucher
Capture the line item from the supplier invoice. 
On the bottom right, select the button named Auto Allocation.
The auto allocation option will set the cost based on a weighted average value and apply it to all the items on the GRV. 
For a single item, the full external charge amount will be allocated part of the cost to the item. 
With more than 1 line item, the system allocated the additional costs accordingly. 




If you are happy with the amount captured, select the Accept button. 
Warning
Note:
Just note that the amount that is captured here is inclusive of VAT. 




After the GRV has been processed, an additional page displays the GRV External Charge. 

    • Related Articles

    • Goods Received Voucher (GRV) | External Charges

      What is a external charge/cost? An external cost is the cost incurred by an individual, firm or community as a result of an economic transaction which they are not directly involved in. External costs, also called ‘spillovers’ and ‘third party costs’ ...
    • Processing | Goods Receiving | Print of GRV Labels

      Question: Is it possible to print labels when performing a Goods Received Voucher? Answer: Yes, it is possible but the settings needs to be enabled in IQ. Navigation: Click on Utilities Click on Setup Click on Company Details Click on the Default ...
    • Processing | Invoicing | Change of debtor's account

      Version: Applies to version Question Is it possible to change a debtor's account in the invoicing module? Note Please note this article applies to all the processing modules in Answer Yes, it will apply for the following processing modules: ...
    • Processing | Return Goods to Supplier and Credit Notes | Bypass Original Document

      Question: We recently updated IQ to the latest version 2025.3.0.1, but now, when we want to create a credit note, the system does not allow us to skip the 'Load of original document'. Answer: This was due to a feature added in the batch control ...
    • Loyalty Plus | Processing | Invoicing

      You are able to perform loyalty sales via the Point of Sale Account sales and the Processing Invoicing modules. Navigate to Processing and select Invoicing. Select the customer or debtor. To enter the Loyalty customer click Actions followed by ...